The Guyana government is rejecting a US$50 million demand by American joint venturers, CH4/LINDSAYCA, for a three-month delay in the installation of electricity generators as part of the 300 megawatt natural-gas fired power plant because other contractors took too long to complete related works. He said CH4/LINDSAYCA wants more time to install four gas turbines of 57 megawatts each — ...