Last Updated on Saturday, 21 November 2026, 11:02 by Written By Denis Chabrol

GPL’s technical teams have now narrowed down the fault to the grounding transformer panel. (GPL picture)The Guyana Power and Light (GPL) on Saturday said it found a fault that has caused a mire than 24-hour long blackout in East Berbice, and damaged parts were being replaced.
“Following continued testing and assessment, technical teams have now narrowed down the fault to the grounding transformer panel. Works are currently underway to replace several defective components, after which further testing of the facility will be conducted to facilitate the safe restoration of electricity supply,” the power company said.
However, GPL indicated that it was too early to say when power would be restored to residents and businesses in Region Six (Esst Berbice-Corentyne).
From the moment the situation developed at the Canefield Substation on Thursday, the utility company says it has been on the ground, with its management and technical teams working around the clock to address the issues and restore electricity supply to affected customers across Berbice.
“An estimated restoration time will be communicated in a subsequent update. GPL remains committed to keeping customers informed as works progress and appreciates their continued patience and understanding,” the powe company said.
GPL also says the work is being undertaken carefully and methodically to ensure that all outstanding technical issues are addressed before electricity supply is safely restored.
GPL says its management team remains fully involved, working alongside the technical team and overseeing the restoration efforts, which continue on around the clock.
The team is headed by its Deputy Chief Executive Officer of Strategic Operations, Mr Bharat Harjohn, and Divisional Director of Transmission and Distribution, Mr Shaun Hamlet, with technical assistance from Kalpataru Projects International Limited.
Since Thursday evening, the power company said GPL’s technical teams have been conducting extensive troubleshooting, inspecting the wiring, electrical panels, busbar and distribution feeders. Several faulty components have been identified and replaced as part of the corrective works.
The company sincerely apologises for the prolonged service interruption and assures customers that every effort is being made to resolve the situation as safely and quickly as possible.
Discover more from Demerara Waves Online News- Guyana
Subscribe to get the latest posts sent to your email.