The cost of the natural gas-fired electricity generation and liquids plants is ballooning closer to US$1 billion, now that the United States (US)-headquartered company, LINDSAYCA has demanded an additional US$100 million within the last six months, Prime Minister Mark Phillips said Monday.
During extensive questions by opposition A Partnership for National Unity (APNU) parliamentarians about the repeatedly delayed 300 megawatt power plant at Wales, West Bank Demerara, he said LINDSAYCA’s total demand was now US$200 million of which US$170 million was already paid.
Prime Minister Phillips said as a result the cost has moved from the originally contracted price of US$759 million to US$956 million.
The latest tranche of GYD$24.7 billion was approved by the National Assembly during consideration of requests for additional funding for the energy sector.
With this new financing arrangement largely in lieu of arbitration over additional monies that the then joint venture CH/LINDSAYCA had spent on soil stabilisation, it means that LINDSAYCA would be paid an additional US$100 million on top of the 12.8 percent or US$97,152,000 over the original contract sum of US$759 million that government had announced in May, 2026.
Responding to a question from APNU parliamentary leader Dr Terrence Campbell about whether there would be a cap on expenditure with penalties, no further amendments and no requests for additional funds, Mr Phillips said he could not look into the future but he did not “envisage any slippage” and so the contractor would complete the project within the given time-frame. “Of course, in an open book manner, we provide money based on work to be completed towards the the completion of this project,” he said. He said government was now targeting the first quarter of 2027 for start-up of the electricity plant.
The cost of the plant does not include the US$1 billion pipeline that was financed by Exxon Mobil and has to be repaid. Guyana has to repay that American supermajor but gas would be provided to the country free of cost.
Phase 2
Prime Minister Phillips also defended government’s decision to sole-source turbines for phase two of the Wales gas-to-energy project with a capacity of 260 megawatts. He said government had already paid 10 percent of the cost of the turbines to the Germany-headquartered manufacturer, Siemens Energy, and with Monday’s approval of approximately US$20.3 million another 10 percent payment would be made. Mr Phillips said because of the demand for turbines and Siemens Energy was the only company that was manufacturing them, government opted to sole-source them instead of requesting competitive bids. “In order to ensure we keep it in schedule-2030 for phase two-we are forced to do long-lead procurement, which is pay up some money up front, and you secure the commitment from the supplier. The rest of money will be paid afterwards,” he said.