The Guyana Power and Light Inc. (GPL) said at about 6:48 PM that works at the Canefield substation have been completed and incremental electricity restoration has commenced in East Berbice.
The power company said customers in Canefield to Williamsburg and Canefield to Kortberaadt would gradually receive power. New Amsterdam has already been repowered, GPL said.
“This repowering exercise will continue until power has been restored to all affected areas,” the power company said.
GPL says its technical teams are continuing the careful, phased restoration of the network to return electricity safely to the remaining affected communities. “GPL fully understands the hardship and frustration caused by this prolonged service interruption and sincerely apologises to our customers. We deeply appreciate your continued patience and understanding as restoration progresses.”
President Irfaan Ali earlier Saturday said those responsible would have to give reasons for the prolonged power outage, the worst in GPL’s recent history. “There will be a full and thorough review of the circumstances that led to this failure, the adequacy and effectiveness of GPL’s response, and the measures necessary to prevent a recurrence,” he said in a statement.